 Tools you need to prepare before installation: Wrench toolbox, gear oil, tow rope, forklift, mobile truck crane.

 

5t-overhead-crane-installation-guide

 

The overhead crane installation steps are as below:

Fill the gearbox oil – end carriage connection – buffer installation – C rail installation – electric box installation – electric hoist installation – adjust the gap to 3~5mm – festoon installation – crane hoisting – conductor rail installation – installation finished.

 

There is an installation guide video for your better understanding.

 


https://www.weihuacraneglobal.com/news/Installation-Guide-of-Single-Girder-Overhead-Crane.html